Excelsior Springs Community Center Update

Excelsior Springs Community Center Special Projects Coordinator Jesse Hall sent an update on the progress taking place on the outside expansion to the Center.
This week
1. Deck steel set, as well as three concrete pours.
2. Spillway (Rip Rap) and final dam prep took place at Powell Lake.
3. Final trench drain set on deck and footing poured.
4. Parking lot extension excavation continued.
Next week
1. Final deck pour is scheduled for Tuesday.
2. Concrete between trench drains and dome footings will be completed.
3. Dome entryway and completion of dome footing will take place.
4. Topsoil will be spread at Century Park. Seeding will begin.
5. Steel will continue to be set outside dome footings in preparation for additional concrete.
6. Final third party inspection has been scheduled for the dam at Powell Lake.
As we dreamed about the addition of Phase 2 we listed the following benefits: it would provide Excelsior Springs:
*Opportunity to make new friends.
*Exercise opportunities for all.
* Perfect for a relaxing family outing.
*Close to home.
*Increases the value of your home.
*A reason to go outside.



We keep the local news free thanks to advertisers and individual contributions!
- Excelsior Springs Fire Department joins Meals & a Visit Program to boost home safety for meal recipients
- Missouri’s $216M rural health award draws praise and caution from rural hospital leaders
- Community Groups Launch Next Phase of Excelsior Springs Schools Strategic Plan
- Judge grants Rhodus intervention motion, gives residents more time in Mosby–Excelsior annexation fight
- Slightly Off Broadway opens 2026 season with “Steel Magnolias”
- Lady Tigers Win Brookfield Wrestling Title, Crown Three Champs (Jan. 19-23)